A Remarkable Journey:

Bhairavnath Sugar Works Limited was incorporate vide certificate of incorporation no. 25-14725 dated 4th April, 2000 with Registrar of Companies, Maharashtra at Pune.

The Company has been promoted by Mr. Tanaji Jayawant Sawant with the main object of carrying out the activity of production of sugar and other sugar related activities. The Company commenced its first commercial production in 2008-09 at Sonari, Tal. Paranda, Dist. Osmanabad. The original capacity of the factory was 2500 TCD. Subsequently, this capacity was increased in stage and is currently 3500 TCD. Beside this plant the Company has set up 2500 TCD new Sugar plant at Vihal, Tal. Karmala, Dist. Solapur in 2011-12 and has also set up another 2500 TCD Sugar Plant at Lavangi, Tal. Mangalvedha, Dist. Solapur, in 2013-14. Company has entered into Collaboration Agreement for running sugar factory with Shivshakti Shetkari Sahakari Sakhar Karkhana Ltd, Washi, Dist. Osmanabad having capacity of 1250 TCD in 2012-13. Further, the company has increased the capacity of plant to 2500 TCD and running the same from year 2013-14. The Company has purchased another 2500 TCD Sugar plant at Alegaon in 2017-18.

Thus the total installed capacity of BSWL is 12250 TCD. The company has also co- generation plant at Sonari, Vihal, Lavangi and Alegaon unit. The aggregate power generation capacity of all four cogeneration power plants is put together 53 MW. Here is the list of major events in the company's history:

Year Milestone
2000 Incorporation of the Company in the name of Bhairavnath Sugar Works Limited.
2006 The Company commenced business under the dynamic leadership of Mr. Tanaji Jayawant Sawant and his professional team.
2008-09 Setting Up of 2500 TCD Sugar Plant and 14.5 MW Co-generation Plant At Post Sonari, Tal. Paranda, Dist. Osmanabad.
2009 Commencement of 1st Crushing Season of Sonari Unit
2010 Expansion of capacity of Sonari Unit to 3500 TCD.
2010-11 Setting Up of 2500 TCD Sugar Plant and 12 MW Co-generation Plant At Post Vihal, Tal. Karmala, Dist. Solapur.
2011 Commencement of 1st Crushing Season of Vihal Unit
2013 Entered into Collaboration Agreement for running sugar factory with Shivshakti Shetkari Sahakari Sakhar Karkhana Ltd, Washi, Dist. Osmanabad having capacity of 1250 TCD.
2013 • Setting Up of 2500 TCD Sugar Plant and 14.5 MW Co-generation Plant At Post Lavangi, Tal. Mangalvedha, Dist. Solapur
• Setting up 30 KLPD Molasses based distillery for manufacture of Industrial Alcohol at Sonari Unit.
2014 Commencement of 1st Crushing Season of Lavangi Unit